Project Update: Arroyo Terrace Apartments

arstaffNews

Exciting progress continues.

Building 1 is gearing up for exterior siding and stucco, while Building 2 has completed framing with MEP rough-ins in progress. The foundation for Building 3 is now complete, and framing officially began this week. Large retaining walls are complete, and off-site street and sidewalk improvements are underway.

Thank you to the Abbott | Reed team and our trade partners for their outstanding efforts and commitment to a great build.

Developed by the Housing Authority of San Luis Obispo and designed by RRM Design Group, Arroyo Terrace will deliver 63 essential residential units to the Central Coast community.